Explore our comprehensive portfolio of engineering projects across Nepal
| # | Project Name | Client | Status |
|---|---|---|---|
| 1 | Upper Madi-0 Hydropower project (43 MW), Kaski | Annapurna Power Company Pvt. Ltd. | Construction supervision Ongoing |
| 2 | Mid Hongu Khola B Hydropower project -22.9 MW, Solukhumbu | Gaurishankhar Hydropower Pvt. Ltd. | Construction supervision Ongoing |
| 3 | Mid Hongu Khola A Small hydropower project -22 MW, Solukhumbu | Apex Makalu Hydropower Pvt. Ltd. | Construction supervision Ongoing |
| 4 | Khani Khola Hydroelectric Project (30MW), Dolakha | Sasha Engineering Hydropower Pvt. Ltd. | Construction supervision Ongoing |
| 5 | Doodhpokhari Chepe Khola Hydropower Project- 11.0 MW, Gorkha | Doodhpokhari Chepe Hydropower Pvt. Ltd. | Construction supervision works Ongoing |
| 6 | Syarpu Small Hydropower Project, 3.3 MW, Rukum | Syarpu Power Company Limited | Construction Supervision ongoing |
| 7 | Kabeli - A Hydroelectric Project (37.6 MW) | Kabeli Energy Limited | Partial Construction supervision works Ongoing |
| 8 | Upper Irkhuwa Khola Hydropower project -14.5 MW, Bhojpur | Aarati power Limited | Partial Construction supervision works Ongoing |
| 9 | Sagu Khola Hydroelectric Project -20 MW, Dolakha | Himparbat Hydropower Pvt. Ltd. | Partial Construction supervision works Ongoing |
| 10 | Buku Khola Small Hydropower Project - 6.0 MW, Okhaldhunga | Applo Hydropower Company Pvt. Ltd. | Construction supervision works Ongoing |
| 11 | Irkhuwa Khola B Small hydropower project -15.52 MW, Bhojpur | Baraha Multipower Pvt. Ltd | Partial Construction supervision works Ongoing |
| 12 | Sangu (Sorun) Khola -1 Hydropower Project -5.0 MW, Dolakha | Kalinchowk Hydropower Pvt. Ltd. Galkhupakha, Kathmandu | Partial Construction supervision works Ongoing |
| 13 | Phedi Khola (Tumlung) Small Hydropower Project, 4.3 MW, Bhojpur | Phedi Khola Hydropower Company Pvt. Ltd. | Partial Construction supervision works Ongoing |
| 14 | Super Sabha Khola Small Hydropower Project, 4.1 MW, Sankhuwasabha | Sankhuwasabha Power Development Pvt. Ltd. | Construction supervision works Ongoing |
| 15 | Mid Rawa Khola Hydropower Project, 2.5 MW, Khotang | Halesi Urja Pvt. Ltd. | Construction supervision works Ongoing |
| 16 | Super Sabha Khola A Hydropower Project, 9.5 MW, Sankhuwasabha | Sankhuwasabha Power Development Pvt. Ltd. | Construction supervision works Ongoing |
| 17 | Lower Selang Khola Small hydropower Project 1.5 MW, Sindhupalchowk | Sewa Hydropower Ltd. | Partial Construction supervision works Ongoing |
| # | Project Name | Client | Status |
|---|---|---|---|
| 1 | Sani Bheri-3 hydropower Project (46.72 MW), Rukum | Sanibheri Hydropower Pvt. Ltd. | Ongoing |
| 2 | Bhotekoshi - 5 Hydroelectric Project (46 MW) | Kalika Energy Ltd. | Ongoing |
| 3 | Gunsa-Tamor Hydroelectric Project (43 MW), Panchthar | Nepal Hydroelectric Venture Pvt. Ltd. | Ongoing |
| 4 | Upper Mewa A Hydroelectric Project, 31.92 MW, Taplejung | Surya Holding Pvt. Ltd. | Ongoing |
| 5 | Hongu Khola-1 Hydropower project (30 MW), Solukhumbu | I.B Energy Pvt. Ltd | Ongoing |
| 6 | Sani Bheri-3 Cascade HEP (30 MW), Rukum | Sanibheri Hydropower Pvt. Ltd. | Ongoing |
| 7 | Induwa Khola PROR HEP (23.4 MW), Sankhuwasabha | Vision Tesla Power Pvt. Ltd. | Ongoing |
| 8 | Mudi Khola Hydropower Project - MW, Myagdi | Carbonless Energy Fund Pvt. Ltd, Dillibazar, Kathmandu | Ongoing |
| 9 | Jaldi gad Hydropower Project (21 MW), Rukum | Shangri-La Hydropower Pvt. Ltd. | Ongoing |
| 10 | Upper Mudi khola Hydropower Project - 12.7 MW, Myagdi | Fresh Water Energy Company Ltd | Ongoing |
| 11 | Kunaban Khola Hydropower Project (20 MW) | Sushmit Energy | Ongoing |
| 12 | Upper Seti-1 Hydropower project (13 MW), Kaski | Shrestha Energy Solution Pvt. Ltd | Completed |
| 13 | Myagdi B Hydropower Project (12.5 MW) | Sushmit Energy | Ongoing |
| 14 | Sabha Khola –A Hydropower Project (10.4 MW), Sankhuwasabha | Dipsabha Hydropower Pvt. Ltd, Koteshwor -35, KTM | Ongoing |
| 15 | Upper Daraudi Hydropower Project - 9.2 MW, Gorkha | Green Gorkha Energy Ltd | Ongoing |
| 16 | Khimti Ghwang Small Hydropower Project (9 MW), Ramechhap | Nilganga Hydropower Project Company Pvt. Ltd | Ongoing |
| 17 | Sona Khola Hydropower Project (9.0 MW), Taplejung | Himali Hydro Fund Pvt. Ltd. | Ongoing |
| 18 | Upper- Piluwa Khola-1 Hydroelectric Project (7.7 MW), Sankhuwasabha | Menchhiyam Hydropower Pvt. Ltd | Ongoing |
| 19 | Malta Bagmati Hydropower Project (6.5 MW), Makwanpur | Bagmati Water Energy Pvt. Ltd. | Ongoing |
| 20 | Lower Bhim Khola Cascade Hydropower Project (6.05 MW), Baglung | Shikhar Power Company Pvt. Ltd | Ongoing |
| 21 | Lower Thulo Khola Hydroelectric project (4.75 MW), Myagdi | Chitwan Energy Limited | Ongoing |
| 22 | Super Machha Khola Hydroelectric Project (4.6 MW), Gorkha | Budhigandaki Hydropower Project Pvt Ltd | Ongoing |
| 23 | Manahari Khola Hydroelectric Project PROR (4.5 MW), Makwanpur | Dynamic Power Pvt. Ltd. | Ongoing |
| 24 | Super Sabha Khola Small Hydropower Project (4.1 MW), Sankhuwasabha | Sankhuwasabha Power Development Pvt. Ltd. | Ongoing |
| 25 | Upper Madi-0 Hydropower project (43 MW), Kaski | Annapurna Power Company Pvt. Ltd. | Completed |
| 26 | Kabeli - A Hydroelectric Project (37.6 MW), Pachthar | Kabeli Energy Limited | Completed |
| 27 | Mid Hongu Khola B Hydropower Project (22.9 MW), Solukhumbu | Gaurishankhar Hydropower Pvt. Ltd. | Completed |
| 28 | Mid Hongu Khola A Hydropower Project (22 MW), Solukhumbu | Apex Makalu Hydropower Pvt. Ltd. | Completed |
| 29 | Thulo Khola Hydropower Project (21.3 MW), Myagdi | Syamukta Urja Limited | Completed |
| 30 | Sagu Khola Hydroelectric Project (20 MW), Dolakha | Himparbat Hydropower Pvt. Ltd. | Completed |
| 31 | Upper Solu Hydropower Project (19.8 MW), Solukhumbu | Beni Hydropower Project Pvt. Ltd. | Completed |
| 32 | Irkhuwa Khola B Small hydropower project (15.52 MW), Bhojpur | Baraha Multipower Pvt. Ltd | Completed |
| 33 | Upper- Thulo Khola -A Hydropower Project (15 MW), Myagdi | Thulo khola Hydropower project Pvt. Ltd. | Completed |
| 34 | Upper Irkhuwa Khola Hydropower Project -14.5 MW, Bhojpur | Aarati power Ltd. | Completed |
| 35 | Doodhpokhari Chepe Hydropower Project (11 MW), Gorkha | Doodhpokhari Chepe Hydropower Pvt. Ltd. | Completed |
| 36 | Upper Daraudi -C Small Hydropower Project (9.83 MW), Gorkha | Kalika Construction (Pvt) Ltd Kalika Tower, Baluwatar,KTM | Completed |
| 37 | Super Mai-A Hydropower Project (9.6 MW), Ilam | Sagarmatha Hydropower Company Pvt. Ltd | Completed |
| 38 | Daram Khola Hydroelectric Project (9.6 MW), Baglung | Daram Khola Hydro Energy Co. Ltd. | Completed |
| 39 | Mid- Solu Khola Hydropower Project (9.5 MW), Solukhumbu | Mid-Solu Hydropower Project Pvt Ltd | Completed |
| 40 | Super Chepe Khola Hydropower Project (9.05 MW), Gorkha | Ridge Line Energy Pvt. Ltd | Completed |
| 41 | Upper Daraudi -B Small Hydropower Project (8.3 MW), Gorkha | Kalika Construction (Pvt) Ltd Kalika Tower, Baluwatar,KTM | Completed |
| 42 | Super Mai Hydropower Project (7.8 MW), Illam | Super Mai Hydropower Company Pvt. Ltd | Completed |
| 43 | Garchayang Khola Hydropower Project (6.6 MW), Kaski | Citizen Hydropower Company Pvt. Ltd | Completed |
| 44 | Daraudi Khola -A Hydropower Project (6 MW), Gorkha | Daraudi Kalika Hydro Pvt. Ltd. | Completed |
| 45 | Buku Khola Small Hydropower Project (6.0 MW), Okhaldhunga | Applo Hydropower Company Pvt. Ltd. | Completed |
| 46 | Sagu Khola -1 Hydropower Project (5.5 MW), Dolakha | Himparbat Hydropower Pvt. Ltd. | Completed |
| 47 | Lankhuwa Khola Small Hydroelectric Project (5.0 MW), Sankhuwasabha | Sabhapokhari Hydropower Pvt. Ltd. | Completed |
| 48 | Buku Kapti Hydropower project (5 MW), Okhaldhunga | Himstar Urja Pvt. Ltd | Completed |
| 49 | Sangu (Sorun) Khola -1 Hydropower Project (5.0 MW), Dolakha | Kalinchowk Hydropower Pvt. Ltd. Galkhupakha, Kathmandu | Completed |
| 50 | Bhim Khola Small Hydropower Project (4.96 MW), Baglung | Shikhar Power Company Pvt. Ltd | Completed |
| 51 | Upper Machha Khola Hydropower Project (4.55 MW), Gorkha | Bikash Hydropower Company Pvt. Ltd. | Completed |
| 52 | Padam Khola Small Hydropower Project (4.5 MW), Dailekh | Dolti Power Company Pvt. Ltd | Completed |
| 53 | Phedi Khola (Tumlung) Small Hydropower Project (4.3 MW), Bhojpur | Phedi Khola Hydropower Company Pvt. Ltd. | Completed |
| 54 | Rani Jamara Kulariya Irrigation Project (4 MW), Kailali | Rani Jamara Kulariya Irrigation Project | Completed |
| 55 | Puwa Khola –One Hydropower Project (4MW), Ilam | Puwa Khola –One Hydropower project Pvt. Ltd., Bagbazar | Completed |
| 56 | Upper Lohore Small Hydropower Project (4.0 MW), Dailekh | Upper Lohore Small Hydropower Project Co. Pvt. Ltd. | Completed |
| 57 | Dwari Khola Small Hydropower Project (3.75 MW), Dailekh | Bhugol Energy Development Pvt. Ltd. | Completed |
| 58 | Syarpu Small Hydropower Project (3.3 MW), Rukum | Syarpu Power Company Limited | Completed |
| 59 | Super Mai Cascade Hydropower Project (3.0 MW), Ilam | Mai khola Hydropower Pvt. Ltd | Completed |
| 60 | Upper Rawa Small Hydropower Project (3.0 MW), Khotang | Rawa Energy Development Company Pvt. Ltd | Completed |
| 61 | Daram Khola-A Hydrelectric Project (2.5 MW), Baglung | Sayapatri Hydropower Co. Ltd | Completed |
| 62 | Mid Rawa Khola Hydropower Project (2.5 MW), Khotang | Halesi Urja Pvt. Ltd. | Completed |
| 63 | Lower Selang Khola Small Hydropower Project (1.5 MW), Sindhupalchowk | Sewa Hydropower Ltd. | Completed |
| 64 | Lower Chhote Khola Small Hydropower Project (1 MW), Gorkha | Pashupati Environmental Power Co. Pvt. Ltd. | Completed |
| 65 | Suspa Bhukhari Small HP (1 MW), Dolkha | Suspa Bhukhari HP Co. Pvt. Ltd. | Completed |
| # | Project Name | Client | Status |
|---|---|---|---|
| 1 | Humla Karnali Cascade HEP (452 MW + 232.6 MW) | Department of Electricity Development | Ongoing |
| 2 | Lower Chepe Hydropower project (8.74 MW) | Achaleshowr Hydropower Company Pvt. Ltd. | Ongoing |
| 3 | Upper Madi-0 Hydropower Project - (43 MW, Kaski | Annapurna Power Company Pvt. Ltd. | Completed |
| 4 | Sani Bheri-3 hydropower Project - 46.72 MW, Rukum East and West | Sanibheri Hydropower Pvt. Ltd. | Completed |
| 5 | Gunsa-Tamor Hydroelectric Project -43 MW, Pachthar | Nepal Hydroelectric Venture Pvt. Ltd. | Completed |
| 6 | Isuwa Khola Cascade PROR Hydropower Project - 37.7 MW, Sankhuwasabha | Isuwa Energy Pvt. Ltd. | Completed |
| 7 | Hongu Khola-1 Hydropower project -30 MW, Solukhumbu | I.B Energy Pvt. Ltd. | Completed |
| 8 | Upper Dhudh khola Hydropower Project - 30 MW, Manang | Carbonless Energy Fund Pvt. Ltd, Dillibazar, Kathmandu | Completed |
| 9 | Sani Bheri-3 Cascade HEP - 30 MW, West Rukum | Sanibheri Hydropower Pvt. Ltd. | Completed |
| 10 | Mid Hongu Khola B Hydropower Project -22.9 MW, Solukhumbu | Gaurishankhar Hydropower Pvt. Ltd. | Completed |
| 11 | Mid Hongu Khola A Hydropower Project -22 MW, Solukhumbu | Apex Makalu Hydropower Pvt. Ltd. | Completed |
| 12 | Thulo Khola Hydropower Project-21.3 MW, Myagdi | Syamukta Urja Limited | Completed |
| 13 | Upper Myagdi Hydropower Project - 20 MW, Myagdi | Hydro Empire Pvt. Ltd | Completed |
| 14 | Mudi Khola Hydropower Project - 14.5 MW,Myagdi | Carbonless Energy Fund Pvt. Ltd, Dillibazar, Kathmandu | Completed |
| 15 | Upper Seti-1 Hydropower project –13 MW, Kaski | Shrestha Energy Solution Pvt. Ltd | Completed |
| 16 | Upper Mudi khola Hydropower Project - 12.7 MW, Myagdi | Fresh Water Energy Company Ltd | Completed |
| 17 | Doodhpokhari Chepe Hydropower Project -11 MW, Gorkha | Doodhpokhari Chepe Hydropower Pvt. Ltd. | Completed |
| 18 | Upper Daraudi -C Small Hydropower Project - 9.83 MW, Gorkha | Kalika Construction (Pvt) Ltd Kalika Tower, Baluwatar,KTM | Completed |
| 19 | Nimrung Khola Hydropower Project-9.8 MW, Gorkha | Kiran Power Company Pvt. Ltd | Completed |
| 20 | Super Mai-A Hydropower Project-9.6 MW, Ilam | Sagarmatha Hydropower Company Pvt. Ltd | Completed |
| 21 | Mai Beni Hydropower Project-9.51 MW, Ilam | Samling power Company Pvt. Ltd | Completed |
| 22 | Mid- Solu Khola Hydropower Project -9.5 MW, Solukhumbu | Mid-Solu Hydropower Project Pvt Ltd | Completed |
| 23 | Upper Daraudi Hydropower Project - 9.2 MW, Gorkha | Green Gorkha Energy Ltd | Completed |
| 24 | Super Chepe Khola Hydropower Project -9.05 MW, Gorkha | Ridge Line Energy Pvt. Ltd | Completed |
| 25 | Upper Daraudi -B Small Hydropower Project -8.3 MW, Gorkha | Kalika Construction (Pvt) Ltd Kalika Tower, Baluwatar,KTM | Completed |
| 26 | Super Chepe Khola Hydropower Project -9.05 MW, Gorkha | Ridge Line Energy Pvt. Ltd | Completed |
| 27 | Nisi Khola A Hydropower Project - 7.36 MW, Baglung | Nishi Khola Power Limited | Completed |
| 28 | Lower Bhim Khola Cascade Hydropower Project - 6.05 MW, Baglung | Shikhar Power Company Pvt. Ltd | Completed |
| 29 | Bagar Khola Hydropower Project - 5.5 MW, Myagdi | Green Myagdi Energy Limited | Completed |
| 30 | Galkot Daram Hydropower Project - 5MW, Baglung | Galkot Daram Hydropower Pvt. Ltd. | Completed |
| 31 | Lankhuwa Khola Small Hydroelectric Project -5.0 MW,Sankhuwasabha | Sabhapokhari Hydropower Pvt. Ltd. | Completed |
| 32 | Bhim Khola Small Hydropower Project-4.96 MW, Baglung | Shikhar Power Company Pvt. Ltd | Completed |
| 33 | Lower Thulo Khola Hydroelectric project- 4.75 MW, Myagdi | Chitwan Energy Limited | Completed |
| 34 | Super Machha Khola Hydroelectric Project -4.6 MW, Gorkha | Budhigandaki Hydropower Project Pvt Ltd | Completed |
| 35 | Upper Machha khola Hydropower Project - 4.55 MW,Gorkha | Bikash Hydropower Company Pvt. Ltd. | Completed |
| 36 | Padam Khola Small hydropower Project - 4.5 MW, Dailekh | Dolti Power Company Pvt. Ltd | Completed |
| 37 | Super Sabha Khola A Hydropower Project - 4.1 MW, Sankhuwasabha | Sankhuwasabha Power Development Pvt. Ltd. | Completed |
| 38 | Upper Lohore small Hydropower Project - 4.0 MW, Dailekh | Upper Lohore Small Hydropower Project Co. Pvt. Ltd. | Completed |
| 39 | Kintang Khola Hydropower Project - 4.0 MW, Dhading | Vision Hydro Pvt. Ltd. Kathmandu | Completed |
| 40 | Syarpu Small Hydropower Project - 3.3 MW, Rukum | Syarpu Power Company Limited | Completed |
| 41 | Daram -A Hydropower Project -3.0 MW, Baglung | White Gold Hydropower Pvt. Ltd. | Completed |
| 42 | Super Mai Cascade Hydropower Project-3.0 MW,Ilam | Mai khola Hydropower Pvt. Ltd | Completed |
| 43 | Mid Rawa Khola Hydropower Project - 2.5 MW, Khotang | Halesi Urja Pvt. Ltd. | Completed |
| 44 | Lower Rupse khola Hydroelectric Project-1.86 MW, Myagdi | Gulmi Hydro Pvt. Ltd. | Completed |
| # | Project Name | Bank | Owner | Status |
|---|---|---|---|---|
| 1 | Due-Diligence Study Report of Bagmati Small Hydropower project- (Capacity Upgrading from 22 MW to 32 MW), Lalitpur | Nabil Bank Limited | Mandu Hydropower Company Pvt. Ltd., Kamladi, Kathmandu | Ongoing |
| 2 | Due-Diligence Study Report of Upper Seti Hydropower Project (2 0.0 MW), Kaski | Sunrise Laxmi bank limited and Its Consortium | Upper Seti Hydro Private Limited Lalitpur, Nepal | Completed |
| 3 | Due-Diligence Study Report of Miwaje Khola Hydropower Project (4.95 MW), Kaski | Prime Bank Limited | Ma Durga Kali Hydropower Pvt. Ltd. Lalitpur, Nepal | Completed |
| 4 | Due-Diligence Study Report of Super Seti Hydropower Project (2 4.0 MW), Kaski | Nabil Bank and Its Consortium | S.N Energy Power Ltd Mahalaxmi, Lalitpur, Nepal | Completed |
| 5 | Supplementary Due-Diligence Study Report of Isuwa Khola Hydropower Project (97.2 MW), Sankhuwasabha | Sanima Bank and Its Consortium | K.B.N.R Isuwa Power Ltd. | Completed |
| 6 | Due-Diligence Study Report of Aaya Malun Hydropower Project (21.0 MW), Okhaldunga | Sanima Bank and Its Consortium | Aayu Malun Hydro Power Pvt. Ltd. Anamnagar, Kathmandu, Nepal | Completed |
| 7 | Due-Diligence Study Report of Tadi Khola Small Hydropower Power (Capacity Upgrading from (6.0 MW), Nuwakot | Nepal Investment Bank and Its Consortium | Hiraratna Hydropower Power Pvt. Ltd., Shamakhushi | Completed |
| 8 | Due-Diligence Study Report of Ilep -(Tatopani) Khola Hydropower Project 2 3. 675 MW, Dhading | Sanima Bank and Its Consortium | Jalashakti Hydro Company Pvt. Ltd. | Completed |
| 9 | Due-Diligence Study Report of Nilgiri Khola II cascade Hydropower Power Project 71.0MW, Myagdi | Prime Commercial Bank and Its Consortium | Nilgiri khola Hydropower Power Company Ltd, Kamaladi | Completed |
| 10 | Nilgiri -1 Hydropower Power Project 38.0 MW, Myagdi | Prime bank Limited and its consortium | Nilgiri Khola Hydropower Power Company Ltd, Kamaladi | Completed |
| 11 | Due-Diligence Study Report of Upper Rauje Khola Hydropower Power Project 18.0 MW, Solukhumbu | Machhapuchhre Bank And Its Consortium | Hydropower Connection Pvt. Ltd., Kupondole, Lalitpur | Completed |
| 12 | Due-Diligence Study Report of Jogmai Cascade Hydroelectric Project 5.2 MW, Ilam | Nepal Bangladesh Bank | Sanvi Energy Pvt. Ltd. | Completed |
| 13 | Due-Diligence Study Report of Upper Midim Hydropower Power Project 7.5 MW, Lamjung | Kumari Bank and Its Consortium | Bhujung Hydropower Power Pvt. Ltd., | Completed |
| 14 | Due-Diligence Study Report of Puwa II Hydropower Project 4.96 MW, Ilam | Nepal Bangladesh Bank | People's Power Ltd. | Completed |
| 15 | Supplementary Due-Diligence Study Report of Balephi -A Hydropower project- (Capacity Upgrading from 10.6 MW to 22 MW), Sindhupalchowk | Nepal Bangladesh Bank and Its Consortium | Moonlight Hydropower Project Pvt. Ltd, Bijulibazar | Completed |
| 16 | Due-Diligence Study Report of Balephi -A Hydropower Project 10.6 MW, Sindhupalchok | Nepal Bangladesh Bank and Its Consortium | Moonlight Hydropower Project Pvt. Ltd, Bijulibazar | Completed |
| 17 | Due-Diligence Study Report of Tadi khola Small Hydropower Power Project 5.0MW, Nuwakot | Nepal Investment Bank and Its Consortium | Hiraratna Hydropower Power Pvt. Ltd., Shamakhushi | Completed |
| 18 | Due-Diligence Study Lower Midim Khola Hydropower Project-1.0 MW Lamjung | Machhapuchhre Bank Limited | Lower Midim Khola Hydropower Company Pvt. Ltd., Kathmandu | Completed |
| 19 | Supplementary Due-Diligence Study Report of Bagmati Small Hydropower project- (Capacity Upgrading from 20MW to 22 MW) Lalitpur | Nepal Prime Commercial Bank and Its Consortium | Mandu Hydropower Company Pvt. Ltd., Kamladi, Kathmandu | Completed |
| 20 | Supplementary Due-Diligence Study Report of Lower Modi Khola Hydroelectric Project (20 MW), Parbat | Sunrise Bank Limited and Its Consortium | Modi Energy (P.) Ltd. | Completed |
| 21 | Supplementary Due-Diligence Study Report of Madkyu Khola Hydropower Project 13MW, Kaski | Nepal Bank Limited and Its Consortium | Sikles Hydropower Pvt. Ltd, Pokhara | Completed |
| 22 | Supplementary Due-Diligence Study Report of Chake khola Hydropower Project 3MW, Ramechhap | Nepal Bank Limited and Its Consortiu m | Garjhang Hydropower Pvt. Ltd, Bijulibazar | Completed |
| # | Project Name | Bank | Owner | Status |
|---|---|---|---|---|
| 1 | Rahughat Mangale Hydroelectric Project (35.5 MW), Myagdi | Nepal Kumari Bank and its consortium | Tundi Power Company Limited | Ongoing |
| 2 | Upper Rahughat HEP (48.5 MW), Myagdi | Nepal Kumari Bank and its consortium | Tundi Power Company Limited | Ongoing |
| 3 | Middle Mewa Hydropower Project 71.0 MW, Taplejung | Himalayan bank Limited and its consortium | Mewa Developers Pvt. Ltd., Sanepa | Ongoing |
| 4 | Nilgiri -1 Hydropower Power Project 38.0 MW, Myagdi | Prime bank Limited and its consortium | Nilgiri Khola Hydropower Power Company Ltd, Kamaladi | Ongoing |
| 5 | Super Nyadi Hydropower project (40.27 MW), Lamjung | NMB Bank Limited and its Consortium | Suri Nyadi Power Limited | Ongoing |
| 6 | Upper Myagdi Hydropower project (37 MW), Myagdi | Siddhartha Bank Limited and its Consortium | Hydro Empire Limited | Ongoing |
| 7 | Middle Mewa Hydroelectric Project 50.0 MW, Taplejung | Citizen bank Limited and its consortium | United Modi Hydropower Pvt. Ltd. | Ongoing |
| 8 | Nyasim Khola Hydropower Project (35.0MW), Sindhupalchowk | Sanima bank Limited and its consortium | Sita Hydropower Company Pvt. Ltd. | Ongoing |
| 9 | Chauri Khola Hydropower Project (6 MW), Kavre | Rastriya Banijya Bank Limited | Himalayan Water Resources and Energy Development Company (P). Ltd | Ongoing |
| 10 | Suni Gad Hydropower power project (11.05 MW), Bajura | Sanima bank Limited and its consortium | Omega Energy Development Pvt. Ltd. | Ongoing |
| 11 | Lower Indrawati Hydropwer Projec (4.5MW), Sindhupalchowk | Joti Bikash Bank Limited | National Hydropower company Ltd. | Ongoing |
| 12 | Tadi Khola Small Hydropower Power (6.0 MW), Nuwakot | Nepal Investment Mega Bank Limited | Hiraratna Hydropower Power Pvt. Ltd., Shamakhushi | Ongoing |
| 13 | Upper Suri Khola Hydroelectric Project (7.0 MW), Dolakha | Sanima bank Bank Limited | Makaer Jitumaya Suri Khola Hydropower Ltd. | Completed |
| 14 | Kabeli-B1Cascade Hydroelectric Project (9.94 MW), Pachthar | Bank of Kathmandu and its consortium | Arun Valley Hydropower Development LTD. | Completed |
| 15 | Solukhola (Dhudh Khosi) Hydroelectric Project- 86 MW, Solukhumbu | Nepal Investment bank Limited and its consortium | Sahas Urja Ltd, Hattisar, Kathmandu | Completed |
| 16 | Nilgiri Khola II cascade Hydropower Power Project 71.0 MW, Myagdi | Prime bank Limited and its consortium | Nilgiri Khola Hydropower Power Company Ltd, Kamaladi | Completed |
| 17 | Upper Hewa Khola Hydropower Project -8.5 MW, Sankhuwasabha | NMB Bank Limited and its consortium | Upper Hewa Khola hydropower company Pvt. Ltd. | Completed |
| 18 | Kalanga Gad Hydroelectric Project (15.33 MW), Bajhang | NMB Bank Limited and its Consortium | Kalanga Hydro Pvt. Ltd.. (KHPL) | Completed |
| 19 | Seti Khola Small Hydropower Project (3.5 MW), Parbat | Siddhartha Bank Limited | Parbat Paiyunkhola Hydropower Company Pvt. Limited | Completed |
| 20 | Suri Khola Hydroelectric Project (7.0 MW), Dolakha | Prabhu Bank Limited | Makaer Jitumaya Suri Khola Hydropower Ltd. | Completed |
| 21 | Bagmati Small Hydropower project- 22 MW, Lalitpur | Prime Commercial Bank Limited and its consortium | Mandu Hydropower Company Pvt. Ltd., Kamladi, Kathmandu | Completed |
| 22 | Jeuli Gad Small Hydropower Project-966.0 KW, Doti | Machhapuchhre Bank Limited | Rangun Khola Hydropower Pvt. Ltd., Kathmandu | Completed |
| 23 | Upper Khorunga khola Small Hydropower Project (7.5 MW), Terhathum | Machhapuchhre Bank Limited | Terhathum Power Company (P) Ltd. | Completed |
| # | Project Name | Type of Work | Client | Status |
|---|---|---|---|---|
| 1 | 220 KV Transmission Line Project, Thulokhola Hydropower Project, 21.3 MW, Myagdi | Detail Design, Drawing and Cost Estimation | Samyukta Urja Limited | Completed |
| 2 | 33kV Transmission Line Project of Bhimkhola Small Hydropower Project, 4.96 MW, Baglung | Detail Design, Drawing and Cost Estimation | Shikar Power Development Limited | Completed |
| 3 | 33kV Transmission Line Project of Upper- Piluwa Khola-1 Hydroelectric Project (7.7 MW) | Detail Design, Drawing and Cost Estimation | Menchhiyam Hydropower Pvt. Ltd | Completed |
| 4 | 33kV Transmission Line Project of Super Chepe Khola Hydropower Project (9.05 MW) | Detail Design, Drawing and Cost Estimation | Ridge Line Energy Pvt. Ltd. | Completed |
| 5 | 33kV Transmission Line Project of Sona Khola Hydropower Project, (9 MW) | Detail Design, Drawing and Cost Estimation | Himali Hydro Fund Ltd. | Completed |
| 6 | 33kV Transmission Line Project of Buku Kapti Hydropower Project | Detail Design, Drawing and Cost Estimation | Himstar Urja Company Pvt. Ltd. | Completed |
| 7 | 33kV Transmission Line Project of Upper Lohore Small Hydropower Project 4.0 MW, Dailekh | Detail Design, Drawing and Cost Estimation | Upper Lohore Small Hydropower Project Co. Pvt. Ltd. | Completed |
| # | Project Name | Type of Work | Client | Status |
|---|---|---|---|---|
| 1 | IEE Study of Sani Bheri 3 Cascade Hydropower Project (30 MW), Rukum West | IEE Study | Sani Bheri Hydropower Pvt. Ltd. | Ongoing |
| 2 | IEE Study of 8km-220 kv Transmission Line Project of Thulokhola Hydropower Project, 21.3 MW, Myagdi | IEE Study | Samyukta Urja Limited | Completed |
| 3 | Brief Environment Study of 33 kV transmission line of Bhim Khola Small Hydroelectric project, 4.96 MW | Brief Environment Study | Shikar Power Development Limited | Completed |
| 4 | IEE Study of Bhirkhet - Badakhola -Bansi- Kashikadh Sadak, 15 km at Mahabu Rural Municipality-02,03 & 04, Dailekh (12.3 km) | IEE Study | Infrastructure Development Office, Dailekh | Ongoing |
| 5 | IEE Study of Pankot - Talkot Road project, 25 km, Jayaprithivi Municipality, Masta Gaunpalika and Talkot Gaunpalika, Bhajang, (22 km) | IEE Study | Infrastructure Development Office, Bhajang | Ongoing |
| # | Project Name | Type of Work | Client | Status |
|---|---|---|---|---|
| 1 | Detailed Engineering Survey, Geotechnical, Hydrological Investigation and detailed Design of Marsyangdi khola Bridge Along Dhikurpokhari-Pishang-Ghyaru Motorable Bridge, Manag | Detail Survey, Geotechnical and Hydrological investigation and Detail design Detailed design of bridge | Infrastructure Development office, Manang, Nepal | Completed |
| 2 | Detailed Engineering Survey, Geotechnical, Hydrological Investigation and detailed Design of Rhorang Khola Bridge Along Manje- Khangsaar Road, Manag | Detail Survey, Geotechnical and Hydrological investigation and Detail design Detailed design of bridge | Infrastructure Development office, Manang, Nepal | Completed |
| 3 | Consulting service for Detailed Engineering Survey, Soil Investigation and detailed Design of Gaurighat bridge Babiyachaur-3 Baddichur-babiyachaur - Jamughat-Tatopani Road, Surkhet | Detail Survey, Geotechnical and Hydrological investigation and Detail design Detailed design of bridge | Road Division office Surkhet | Completed |
| 4 | Detailed design of bridge over Nagmati river near mulkharka and road from Nagmati Dam to Bhanjyag and review of existing road from sundarijal to Dam axis of Nagmati Dam Project | Detailed design of bridge and road | Nagmati Dam Project Guheshwori, Kathmandu | Completed |
| 5 | Consulting service for Detailed Engineering Survey, Soil Investigation and detailed Design of Gaurighat bridge Babiyachaur-3 Baddichur-babiyachaur - Jamughat-Tatopani Road, Surkhet | Detail Survey, Geotechnical and Hydrological investigation and Detail design Detailed design of bridge | Road Division office Surkhet | Completed |
| 6 | Feasibility Study of Shaktikhor Majimtar Road Tunnel | Feasibility study of road tunnel | Quality & Research Development center, DOR, Chakupat | Completed |
| 7 | Detailed Engineering Survey, DCP Test, Detailed Design Cost Estimate and DPR preparation of Dedgaun-Raptigaun - Boudikhola - Birshaura-Deurali-Jhyalbas Road -24 KM | Detailed Project Report (DPR) | Infrastructure Development Office Kawashoti, Nawalprasi (Bardaghat Susta East) | Completed |
| 8 | Preparation of Detailed Project report (DPR) of Yakse Kavrabote to Sobuwa khola Road-3.466 KM | Detail Project Report (DPR) | Aathari Tribeni Rural Municipality Office of Rural Municipal Executive, Hangpang Taplejung | Completed |
| 9 | Dam Safety Training (i)Dam Safety Training for Dam Owner, Safety Manager,Dam Operator. (ii)Dam Safety Training for Stakeholders | Dam Safety Training | Project Implementation (Irrigation -Unit), Guheshwori, Gaurighat,Kathmandu | Completed |
| 10 | Hydrological Study of the Bhotekoshi River | Inception, Field Draft, and Final Report of Hydrological Study of Bhotekoshi River | Department of Water Induced Disaster Prevention, Pulchowk | Completed |
| 11 | Mapping Of Micro Hydropower (MMHP And Preparation Of District Electrification Master Plan (DEMP) | Mapping of Micro hydropower project | AEPC, Khumaltar | Completed |
| 12 | Chitwan national park Building | Structural design, Drawing and preparation of report | Chitwan national Park Kasar, Chitwan | Completed |
| 13 | School of Science & Technology Building, Mid-Western University Surkhet | Structural Reports & Construction Recommendation for the Building | Mid-Western University, Surkhet | Completed |
| 14 | Bajura Water Supply & Sanitation Project | Feasibility Study, Detail Survey & Design (2 Projects) | WSSSDO- Bajura, Martadi | Completed |
| 15 | Rakam Irrigation Project, Surkhet | Feasibility Study, Detail Survey & Design | Mid-Western Irrigation Development Division-3, Surkhet | Completed |
| 16 | Seti River Training Works, Seti River, Doti | Desk Study, Hydrological Study, Section Details, Detail Design and Report Preparation of Seti River | Water Induced Disaster Prevention S.D. No.-5, Doti | Completed |
| 17 | Bajura Water Supply & Sanitation Project | Feasibility Study, Detail Survey & Design (2 Projects) | WSSSDO- Bajura, Martadi | Completed |
| 18 | Design of Elevated Water Tank at Butwal Municipality, Butwal | Final Report on Structural Design, Drawings, Estimate and BOQ of Elevated Water Tank | LUMANTI Support Group for Shelter, Tahachal, Kathmandu | Completed |
| 19 | Jalad River Control Works, Dhanusha | Final Report of Assessment of human dimension of People's Embankment Programme in a Community | DWIDP, Pulchowk, Lalitpur | Completed |
| 20 | River Training Works of Seti River from Girihauka to Tikhatar | Preparation of Master Plan | Water Induced Disaster Prevention Sub-Division, Doti | Completed |
| 21 | Trisuli Trial Bridge, Trisuli Khola, Nuwakot: Type: D Span: 216.0 m | Feasibility Study, Detailed Engineering Survey, Soil Investigation, Hydrological Study, Detail Design, Drawing, Rate Analysis, Cost Estimate and BOQ | MoFALD, DoLIDAR, Suspension Bridge Division | Completed |
| 22 | Sindure Trial Bridge, Sindure, Nuwakot Type: N Span: 227.8 m | Feasibility Study, Detailed Engineering Survey, Soil Investigation, Hydrological Study, Detail Design, Drawing, Rate Analysis, Cost Estimate and BOQ | MoFALD, DoLIDAR, Suspension Bridge Division | Completed |
| 23 | Punyamati Khola RCC Bridge, Banepa Municipality, Kavreplanchok District Span: 45m | Feasibility Study, Detailed Engineering Survey, Soil Investigation, Hydrological Study, Detail Design, Drawings, Rate Analysis, Cost Estimate and BOQ | Banepa Municipality, Banepa, Kavreplanchok | Completed |
| 24 | Budol Shopping Complex | Cost Estimation and Supervision Works | Banepa Municipality, Banepa, Kavreplanchok | Completed |
| 25 | Ground Water Irrigation Project, Mahottari | Hydrological data acquisition and GIS database preparation | DOI, Irrigation Division, Mahottari, | Completed |
| 26 | Preparation of Master Plan of Paudi River | Detail Survey, Master Plan and Report Preparation | Water Induced Disaster Prevention Sub-Division Office, | Completed |
| 27 | Rehabilitation Of Ghatte Khola MHDS | Detail Feasibility Study for Rehabilitation of microhydro | AEPC, Khumaltar | Completed |
| 28 | Mammal Irrigation Project, Dhading | Field & Draft Final Detail Feasibility Study and Report Preparation | Irrigation Feasibility Study & Construction Quality Program, DOI | Completed |
| 29 | Micro Piling for Banepa Shopping Complex | Structural Design, Drawings, Rate Analysis, Cost Estimation and Supervision | Banepa Municipality, Banepa, Kavreplanchok | Completed |
| 30 | Presidental College | Master plan | Presidental College, Baneshwor | Completed |
| 31 | Afflux analysis of West Rapti River due to Kalkaluwa bund and laxmanpur Barrage | Numerical analysis | People's Embankment program field office Lamahi,Dang | Completed |
| 32 | Waste water quality test | Waste water quality test and preparation of report | Pokhara Sub-metropolitan New road Pokhara | Completed |